15-Hour Extension Liquid Terminal Sokhna – Basin 3, Sokhna Port

Project Information:
  • Type: Ports & Marines Infrastructure
  • Owner: Sonker Bunkering Company
  • Architect: ATMS
  • Manager: ATMS
  • Contract Value: 6 Millions EGP
  • Status: Completed (2011)

Project Description:


  • Grubbing, Grading & disposal to dump area, total 152,000 M2.
  • Backfill with compaction in layers, total 200,000 M3.
  • Chain link fence 2.5m height, total 1,300 ML & steel gate 6 M wide.
  • EPC the steel structure of a site office 9m x 25 m & car shed, total 12 ton & RC foundation.
  • All internal finishes, Plumbing, air conditioning, furniture, electrical, communications and data networks.
  • External utilities as water supply, sewage drainage piping, soak away, water tank, lighting, soft landscaping & electric generator 150 KVA.